Exoscale
Platform Status

SKS control plane components migration to new deployment platform from 2026-08-17 10:30 CEST to 2026-08-17 12:04 CEST

Scheduled maintenance DE-MUC-1 Managed Kubernetes SKS
2026-08-17 10:30 CEST · 1 hour, 34 minutes

Updates

Resolved

Migration successfully completed

August 17, 2026 · 12:04 CEST
Started

This maintenance is now starting as planned.

August 17, 2026 · 10:30 CEST
Scheduled

We are going to migrate SKS control plane components to a new deployment platform.
We estimate that this operation will take less than 30 minutes to achieve.

No visible impact is expected from a user perspective.
During the maintenance window, both your SKS clusters and the SKS product API will continue to work as expected. The “etcd” backend of your clusters is not in the scope of this migration.

August 13, 2026 · 16:43 CEST