Exoscale
Platform Status

[CH-DK-2] Scheduled Power Maintenance - Redundancy Impact Only from 2024-11-06 14:00 CEST to 2024-11-06 17:00 CEST

Scheduled maintenance CH-DK-2 API Compute Database service DBaaS Managed Kubernetes SKS Network Load Balancer NLB Managed Private Networks
2024-11-06 14:00 CEST · 3 hours

Updates

Resolved

This maintenance has been concluded as planned.

November 6, 2024 · 17:00 CEST
Started

This maintenance is now starting as planned.

November 6, 2024 · 14:00 CEST
Update

Due to on-site personnel availability, the maintenance originally scheduled for 7:00 AM has been postponed to 2:00 PM. The duration and impact remain the same, with only a temporary reduction in redundancy and no expected service impact.

November 6, 2024 · 13:57 CEST
Scheduled

We will be conducting a scheduled power maintenance on our critical racks to enhance system reliability. During this window, redundancy will be temporarily reduced, but no service impact is anticipated. All necessary precautions have been taken to ensure continuous operation

October 31, 2024 · 12:24 CEST

← Back