Exoscale
Platform Status

[CH-GVA-2]Core Network - Hardware replacement from 2024-06-25 04:00 CEST to 2024-06-25 07:53 CEST

Scheduled maintenance Global CH-GVA-2 API Compute Database service DBaaS Managed Kubernetes SKS Network Load Balancer NLB Object Storage SOS DNS Portal Managed Private Networks
2024-06-25 04:00 CEST · 3 hours, 53 minutes

Updates

Resolved

Maintenance has been completed.

Our monitoring is showing that all services are green and no impact was observed with the exception of the TCP reset.

June 25, 2024 · 07:52 CEST
Started

This maintenance is now starting as planned.

June 25, 2024 · 04:00 CEST
Scheduled

As part of our ongoing commitment to improve our core network architecture on a global scale, we are implementing significant changes to our networking infrastructure in CH-GVA-2.

We don’t expect this intervention to have any impact on operations and services, however a TCP session reset could be seen on the ongoing connections a couple of times.

Please be assured that we will provide regular updates on the progress of this deployment. Your satisfaction and uninterrupted service remains our top priority.

June 18, 2024 · 10:26 CEST